The Federal Executive Council (FEC), on Wednesday, approved a total contract sum of N5.485 billion for secretariat buildings in five states and the rehabilitation of the Lower Usuma dam. And that project is the rehabilitation of Lower Usuma Dam Water Treatment Plant Phase Two at the sum of N1,510,206,066. “The contract was originally awarded at N1,017,979,566, the additional sum of N1,510,206,066 approved by FEC brings the total contract sum to N2,528,187,633. “As you know, the water treatment plant is a very important infrastructure project. The contact is to rehabilitate that Treatment Plant which has been in operation for about 30 years.
Source: Nigerian Tribune August 19, 2020 17:48 UTC