By GEORGE MUNENEMore by this AuthorThe Japanese government has expressed concern over delayed resumption of the stalled Sh20 billion Thiba Dam project meant to increase rice production in the giant Mwea Irrigation Scheme in Kirinyaga County. He exuded confidence that Kenya will ensure faster completion of the mega project which is funded by Japan. FINANCESConstruction of the dam stalled this year due to financial constraints which led to the contractor, Strabag International, sending its workers home. Local leaders have previously warned that if the current situation is not resolved, the project risks going the Kimwarer Dam way. He explained that Treasury had agreed to pay Strabag International while asking farmers and local leaders to be patient.