The Kabete-South C tunnel that is expected to boost water supply in the western part of the city will be completed by December. The multimillion-shilling project is 74 per cent complete, Nairobi Water and Sewerage Company managing director Nahashon Muguna said on Monday. "Currently we have the secondary lining of the tunnel with concrete, which is at 21 per cent going on. We also have construction of intakes at Githika, Irati and Maragua, which is ongoing at 46 per cent," Muguna said. "The tank is at 95 per cent completion with only the inlet, outlet, scour and overflow pipes and fittings works pending," Muguna stated.
Source: The Star June 10, 2020 19:52 UTC