During a guided inspection tour over the weekend to Yekepa, Buchanan, and Mount Coffee CLSG Substations, Mines and Energy Minister Gesler E. Murray gathered that contractors have made tremendous progress in getting the transmission facilities ready for full utilization. According to Minister Murray, the completion level of the project is at 97 percent. The Substations are located in Yekepa, Nimba County, Botota, Bong County, Buchanan, Grand Bassa County, Mano, Cape Mount County, and Mount Coffee in Montserrado. According to CLSG Country Manager, Jerry Taylor, four of the five stations are nearly complete and will be ready for the President’s commissioning and dedication in mid-December. The African Development Bank (AfDB), World Bank and other Donor partners of the Liberian Government are working collaboratively to achieve implementation of the CLSG Project by providing grants and loans.
Source: Front Page Africa November 15, 2020 23:48 UTC