Time frame shortened for wind farm decision


An artist’s impression of what the turbines will look like for stage two of the Mahinerangi wind farm from Black Rock Runs Rd. PHOTO: SUPPLIEDMercury Energy has been given a boost to its planned Mahinerangi wind farm expansion by way of a shorter time frame than it asked for. The wind farm was referred to the fast-track process by Mercury Energy last year and accepted for referral in November. The applicant has asked for 63 working days — similar to that of its Southland wind farm, near Wyndham. The convener said although the two projects were broadly similar in scale, the Mahinerangi wind farm was less complex.


Source: Otago Daily Times February 09, 2026 17:48 UTC