more-inThe impasse over land acquisition in Trilokpuri to complete the Majlis Park – Shiv Vihar stretch of the Pink Line continues with locals unwilling to vacate their houses. For now, operations on the rest of the Pink Line (total 38 stations with several interchanging points) will begin sometime between December 2017 and March 2018. 364 affected householdsIn Trilokpuri, 108 plots of Block-15 have a total of 364 affected households. “The Delhi Urban Shelter Improvement Board has allotted an 11,138 sq m land to DMRC for the relocation of the affected persons. However, due to resistance from the locals, the work cannot be started,” said a DMRC spokesperson.
Source: The Hindu August 05, 2017 02:13 UTC