Widening of Parwanoo-Solan highway in Himachal hits Covid hurdle, set to miss second deadlinechandigarhUpdated: Aug 21, 2020 16:27 ISTThe National Highway 22 four-laning project between Parwanoo and Solan is set to miss its extended deadline of September 30, 2020, chiefly due to lack of coordination among the multiple agencies executing it. “Though we haven’t set a new deadline but we hope to complete the work by December-end. March 28, 2018: Work on second stage for 23-km stretch from Solan to Kaithlighat allotted. September 30, 2020: Extended deadline for completion of project that is set to be missed, too. COST FACTOREstimated cost of project’s stage 1: Rs 748.7 croreEstimated cost of stage 2: Rs 598 crore